Tiger Pipeline Expansion

Minimize

petrohawk tiger pipeline expansion
 

Tiger Pipeline Expansion
Energy Transfer Company Petrohawk 1 & Petrohawk 2 Interconnect Meter Stations


Scope of Work:
engineering and drafting services to support the fabrication, bidding, and installation of two (2) 350 MMSCFD receipt metering stations on the U.S. Gulf Coast.

Alliance Engineering provided engineering, design and procurement assistance for two interconnect meter stations. The goal of this project was to provide two interconnect delivery points for the 42” Petrohawk transmission pipeline from the 42” ETC Tiger transmission pipeline.

Equipment: the major equipment installed includes two coalescing filter skids, two dual run ultra sonic meter skids, two RTU/Gas Chromatograph buildings (with backup electrical generation), two flow control valve skids, and two 300 BBL API 12F condensate tanks with secondary containment.


Copyright © 2011 by Alliance Wood Group Engineering, L.P.   |   Privacy Statement  |   Terms Of Use
Reg. No. F-3176
A Wood Group Company