Marsh Creek Expansion Project
Anadarko Petroleum
Scope of Work: Original Scope of work expanded from “owner's engineer” to also include engineering, design, and as-built of the existing meter station.
This project is for the future expansion of Anadarko's operation in the Marcellus Shale region. The scope for this project is the addition of a new 12" pressure reduction skid and a 10" bi-directional ultrasonic meter skid. Construction drawings are being forwarded to Anadarko and TETCO for review and approval, and are expected to be completed in the near future.
Construction will begin following the completion of two remaining wells in the Marsh Creek area.
This project is expected to be completed by July 2011.