Hunter Mesa Station Expansion
Encana / Enterprise Products
Scope of work: Alliance performed detailed engineering, design, project management, procurement, and construction support
Facility: Expansion from 4 to 6 compressor units, upgrading total capacity from 100 MMscfd to 150 MMscfd. The expansion included the installation of additional gas processing facilities.
Equipment:
- 1 CAT3616 / Ariel KBZ / 4 reciprocating compressor skid
- 1 CAT3612 / Ariel KBZ / 4 reciprocating compressor skid
Project description:
Alliance provided detailed engineering and design for the expansion of the Hunter Mesa compressor station.
Originally, Hunter Mesa had 4 CAT3612 / Ariel JGZ / 6 reciprocating compressor units. Alliance provided detailed engineering, design, project management, procurement, and construction support to add 2 new reciprocating compressor units – one CAT3616 / Ariel KBZ / 4 and one CAT3612 / Ariel KBZ / 4 – plus associated equipment.
This project expanded the station’s capacity from 100 MMscfd to 150 MMscfd.
This expansion of the Hunter Mesa compressor station also involved the installation of additional processing equipment; more information about this can be found on the Hunter Mesa page in the "Processing and Production Facilities" section of this website.
Hunter Mesa was completed in July 2011.