Site Map  |  Contact Form  |  Search

Bald Knob Compressor Station

Minimize

bald knob pipeline project image

Bald Knob Compressor Station
Boardwalk
 

Project Description – The goal was to add compression to Fayetteville Shale Gas pipeline to increase peak-day transmission capacity to approximately 1.3 Billion SCFD.   The Fayetteville Shale Lateral consists of approximately 165 miles of 36-inch pipeline. Major equipment included two Solar Mars 100 units with inlet air system and exhaust system, inlet gas scrubbing and discharge gas cooling, and the addition of PCR and auxiliary buildings as well as a plant air system.  The project added 30,500 HP of compression.

Scope of Work – Alliance's scope of work  was to providing project management services including project schedule, cost controls, risk assessment, detailed engineering and design reviews, drafting, and permit support.  Detailed design consisted of all facets of mechanical, civil / structural, electrical, and instrumentation engineering.


Copyright © 2010 by Alliance Wood Group Engineering, L.P.   |   Privacy Statement  |   Terms Of Use
Reg. No. F-3176
A Wood Group Company