Prince TLP
El Paso Energy
GoM – Ewing Bank Block 1003
Scope of Work –
FEED, Detailed Engineering and Design, Procurement, and Fabrication Support
Design Rates –
80 MMscfd
50,000 BOPD
Water Depth – 1,490 ft
Lift Weight – 3,450 Short Tons
Fast Track Schedule –
16 Months from Project Sanction to Offshore Installation
Efficient Hook-up and Extensive Pre-commissioning
Full Hook-up and Integration of Hull and Topsides was Completed and Accepted in only 12 days.
Completion Date – 2000
Records (at time of installation) –
World’s First Dry Tree, Mini TLP
First MODEC Design TLP to be Placed in Service
First Use of Passive Tensioners on TLP Well Risers
First True “Lump Sum” Hull and Mooring System Competitively Bid Between TLP and Spar Contractors