Horn Mountain SPAR
BP / Oxy
GoM – Mississippi Canyon Block 127
Scope of Work –
Conceptual, FEED, Detailed Engineering and Design, Procurement, and Fabrication Support
Design Rates –
70 MMscfd
65,000 BOPD
Water Depth – 5,423 ft
Lift Weight – 4,450 Short Tons
Fast Track Schedule –
- 19 Months from Project Sanction to Topsides Loadout
- 39 Months Total from Drilling Discovery to Pipeline Oil Sales
The Platform Supports a Completion / Workover Rig to Service 14 Well Slots
Completion Date – 2002
Records (at time of installation) –
World’s Deepest Dry Tree Production Platform